the project

category
client

Wightlink

start date

Nov 23, 2023

end date

Feb 10, 2024

innovative process

The challenge

Passenger ferry operator, Wightlink, required a swift, high-quality refit of their catamaran fast-ferry. The objective was to address structural wear, upgrade key systems, and to quickly return the vessel to service.

what we achieved

PDL Marine completed hull repairs, overhauled propulsion and hydraulic systems, refreshed interiors – delivering a full refit under tight timelines with class-compliant testing and certification.

the result

The refit improved vessel safety, reliability, and passenger comfort. Operational downtime was minimised, and the ferry returned to service on schedule, enhancing Wightlink's fleet performance and public service standards.

PDL Marine delivers vessels and metalwork for the most challenging of tasks and conditions